The Project
Design and construction of a Materials Recovery Facility.
The works required the partial demolition of an existing steel framed structure, with amendments to the existing steelwork and erection of a new L shaped 30m x 24m portal framed building undertaken, including the casting of plinths and a new floor slab.
Amendments were undertaken to existing SW and FW drainage, including a packaged foul treatment plant.
A Conder ASP20 sewage treatment plant was installed and commissioned, with an ultimate outfall to a watercourse.
The works on site were undertaken in conjunction with the active waste transfer activities of the client.