Telephone: +44 (0)161 761 5109
https://cheethamhillconstruction.co.uk/sites/default/files/news-images/First%20turbine%20-%20web%20banner%20image_0.jpg

First turbine erected at Frodsham Wind Farm

09 May 2016

The first turbine at Frodsham Wind Farm has been erected.

The Nordex N90 turbine stands 125m in height to the blade tip.

When commissioned, the bespoke turbine can generate up to 2.65MW of electricity. When all 19 turbines are in place the wind farm will have a capacity in excess of 50MW.

Cheetham Hill Construction has acted as Principal Contractor throughout the Balance of Plant works and continues to do so throughout the delivery, installation and commissioning of the Nordex turbines until take over by Frodsham Wind Farm Ltd.

Frodsham Wind Farm - First Turbine

Frodsham Wind Farm - First Turbine

Frodsham Wind Farm - First Turbine

Images courtesy of SUAVE Aerial Photographers

Return to news